Harrison St. waterline replacement project underway

The City of Milwaukie began the waterline replacement project on S.E. Harrison St. between S.E. Campbell St. and S.E. 42nd Ave. in the southern area of the Ardenwald-Johnson Creek neighborhood on Oct. 31, 2011.

Vehicle traffic and residential water service will be impacted by the project. Door hangers will be distributed two days in advance to residents and businesses notifying of water service disruption.

The project will be completed in three phases. The waterline replacement is expected to be competed in December 2011, followed by work on the Harrison St. railroad crossing for the Quiet Zone implementation in early spring 2012, and then reconstructing S.E. Harrison St. from S.E. Campbell St. to S.E. 42nd Ave. in late spring 2012.

For more information about the waterline replacement project, please visit the City of Milwaukie website.